|
Construction of Qinghai-Tibet Railway Advances Smoothly According
to the latest edition of Beijing Review, construction of the Qinghai-Tibet railway,
one of the largest projects in China¡¯s western development, has been going ahead
smoothly since its initiation in mid 2001. On June 29, 2001, construction of the
railway simultaneously began at Golmud in Qinghai Province and Lhasa in Tibet.The
railway is planned to be 1,142 km long, including 1,110 km new line and 32 km
upgraded rail. Starting from Golmud in Qinghai, the railway will pass through
Nachitai, Wudaoliang, Tuotuohe and Yanshiping before climbing over Tanggula Mountain
to get to Amdo, Nagqu, Damxung, Yangbajain and Lhasa in Tibet. Its highest point
is 5,072 meters above sea level. About 960 km of the railway will be built 4,000
meters above sea level and 632 km of its tracks will be laid on permanently frozen
ground. The highland railway will break world records for its height and length.
In addition to the extremely cold weather, lack of oxygen, fragile ecology
and complicated geological conditions, the frequent earthquakes, landslides, mud
and rock flows require complicated techniques to be undertaken for the project,
which is expected to take six years to complete and cost 26.2 billion yuan. With
its capability to handle trains and all-weather service, the railway will play
an indispensable role in improving Tibet¡¯s transportation, promote the economic
and social progress of Qinghai and Tibet, and strengthen contact between China¡¯s
western and eastern regions. Since its initiation in mid 2001, construction has
been going ahead smoothly. Design and Construction of the Project With
the combined efforts of related departments, the project¡¯s prospecting work has
been completed, the design of the line in permafrost section from Golmud to Wangkun
has been done, and that for the Wangkun-Tanggula section is under way. Constructors
have now arrived at worksites and the project has begun in a planned and scientific
way. The 147 km roadbed from Golmud to Wangkun, as well as the Nanshankou Track-laying
Center, has been built, establishing a foundation for the laying of rails next
year. In the meantime, experiments in four sections of permanently frozen earth
have started. Work on 55 bridges and three tunnels have begun and, by the end
of this year, a total investment of 770 million yuan would have been poured in.
So far, 8.8 million cubic meters of stones have been laid on the railway
bed, 5,900 meters of bridges built, 6,000 meters of culverts and more than 500
meters of tunnels dug. Constructors have emphasized quality throughout the course
of the project. They mapped out effective measures, set up a complete management
system and deputed certain responsibilities to everyone and formed a supervisory
group. With these measures taken, the quality of the project is very good. Protection
of the Ecological Environment Owing to its special geological environment
and climate conditions, the Tibetan Plateau has a very fragile ecological environment.
Although the project covers a limited area when compared with the vastness of
the Tibetan Plateau, an environmental protection measure, the strictest in China¡¯s
railway building history, has been carried out. ¡ªProtection of plateau plants.
The Qinghai-Tibet Railway is designed to parallel the Qinghai-Tibet Highway. The
building of sidewalks, management of working sites, utilization of earth, and
determination of which paths vehicles for the project can travel through have
been well planned to prevent local plants from being damaged. Grassed areas of
the worksite will have the grass temporarily removed and returned to the site
when construction work has been completed. In the south of Tanggula Mountain,
plateau plants and local grassed areas will be cultivated for the improvement
of the local environment. Garbage produced in construction and by the daily life
of workers will be collected and buried. ¡ªProtection of rare and endangered
animals and natural reserves. To avoid damage to nature reserves of Hoh Xil, Qumar
River, Chumaerhe and Suojia rivers, the proposed railway must detour from these
areas. To keep away from the Black-neck Crane Nature Reserve, a bypass will be
made. In sections inhabited by wild animals, workers will build 13 land passages
on slopes, 18 passages along bridges and two above the tunnels to provide convenient
conditions for migrating animals to cross the railway line. ¡ªProtection
of lakes and wetlands. To avoid ecological degeneration in wetlands and avoid
a shrinking of its area, planners have done much work to keep the railway away
from wetlands and lakes. If this is impossible, bridges will be their second choice,
rather than roads, as the former is conducive to protecting the ecology of wetlands
and lakes. More culverts will be built to prevent surface water from being blocked
by the railway bed and to allow it to supplement water flowing to the wetlands.
¡ªProtection of the plateau¡¯s frozen earth and natural landscape. To maintain
the stability of frozen earth at the construction sites and to avoid damage to
the natural landscape along the proposed railway, dirt will be gathered together
during construction, and when the project is completed, plants will be grown there.
Frozen earth on the base of the railway will be replaced with unfrozen earth,
and insulation materials will be laid on the bed. In the meantime, measures
will be taken to control the discharge of polluted materials and treat polluted
water. The railway stations are designed to use environment-friendly energy, including
solar energy, electricity and wind energy. ¡ªSupervision of environmental
protection. People from Qinghai and Tibet environmental supervisory departments
will regularly examine construction units and sites to ensure that each part of
the project conforms to the requirements of environment protection. To ensure
implementation of the above-mentioned measures, 1.2 billion yuan will be put into
environmental protection efforts, much higher than what has ever been put into
other railway projects. Extra investment is also needed to bypass nature reserves. Health
Conditions for Constructors The natural hardships of the Tibetan Plateau,
including low air pressure, a shortage of oxygen and its cold, dry and windy weather,
as well as radiation by strong sunshine, can greatly affect the health of construction
workers. To deal with this problem, the Ministry of Health and the Ministry
of Railways have mapped out a series of stipulations and measures to protect the
health of workers constructing the Qinghai-Tibet Railway. Efforts have been made
to introduce them to the special climate situation there, and broaden their knowledge
of self-protection, disease prevention and treatment. The 10,000 workers
and staff have received health checks and training for working in chilly weather
and oxygen-deprived conditions. A system to regularly supervise and report infectious
diseases will be set up. Worker¡¯s safety has been fully taken into account when
selecting machines to be used in the project, and safety protection of the workforce
during the project has been well managed. ¡¡ Dec 03 Xinhuanet
|